Posted on: December 22, 2023

[ARCHIVED] Construction for the Week of December 25th

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Adare Place, Bridge Street, Heffernan Street, Middle Street, Orchard Street, Sheffield Lane, Stilson Avenue and West Center Street
    • Removed, repaired and/or replaced signs on Federal Street, Franklin Street, Meadow Street, Olander Drive and West Street
    • Responded to significant rain event and subsequent flooding events
      • Closed streets along the Mill River including Florence Road, Main Street (Leeds), Meadow Street, Pine Street, Reservoir Road, Spring Street and West Street
      • Deployed stop log structure at the Mill River floodwall on West Street
      • Closed streets along Connecticut River, Oxbow and Mill River Diversion including Old Springfield Road and Pynchon Meadow Road; MassDOT closed Mount Tom Road
  • Lovefield Street remains closed
  • Annual ward street sweeping operations:
    • Continue in Ward 1
    • Complete in Wards 2, 3, 4 and 5
    • Wards will be swept in the following order this year: 5, 4, 3, 2, 1, 7, 6
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed
  • To report an issue with a traffic sign, please submit a request via the Traffic Sign Issue Form

Dryads Green Extension Drainage & Slope Improvements

  • The City has contracted with Geeleher Enterprises Inc. to construct drainage and slope improvements from the end of Dryads Green Extension to the Mill River; work also includes roadway drainage improvements
  • The project is substantially complete
  • Snow storage should be avoided at the dead end so as not to compromise slope integrity
  • Public Works will be on-site continuing post-construction observations throughout the winter

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • The Contractor will not be working on Monday, December 25th
  • I-91 southbound:
    • Daytime right lane closure Tuesday through Friday this week, from 7:00 a.m. to 2:00 p.m., for site access
  • I-91 northbound:
    • No traffic impacts are anticipated this week
  • Route 5:
    • Daytime shoulder closures Tuesday through Friday this week, from 7:00 a.m. to 3:00 p.m., for concrete and slope work; motorist should be alert and use caution as trucks will be entering and exiting the work zone; police details will assist with traffic control
  • Hockanum Road:
    •  Daytime road closure on Thursday this week, from 7:00 a.m. to 2:00 p.m.; a detour (pdf) will be in place
  • Questions about the project should be directed to MassDOT District 2, project #606552

Levee Toe Drain Improvements

  • The City has contracted with Ludlow Construction Co., Inc. for the installation of manholes along the land side of both the Connecticut and Mill River levee systems
  • The project involves the installation of 28 new manholes and inspection of the toe drains running parallel to the levees via CCTV
  • The Contractor will make a pipe repair to a section of toe drain at the end of Henry Street in the coming weeks

Linden Street Sewer Manhole Installation

  • The City has contracted with Geeleher Enterprises Inc. to install a sewer manhole on Linden Street in the vicinity of 2 Linden Street
  • The Contractor has installed the new sewer manhole and a temporary pavement patch
  • Work is substantially complete

Maplewood Terrace Sewer Manhole Installation

  • The City has contracted with Geeleher Enterprises Inc. to install a sewer manhole on Maplewood Terrace in the vicinity of 120 Maplewood Terrace
  • The Contractor has installed the new sewer manhole and a temporary pavement patch
  • Work is substantially complete

State Street Sewer Service Repair

  • The City has contracted with Geeleher Enterprises Inc. to repair two sewer services and a sinkhole in the vicinity of 245 State Street
  • The Contractor will also install a temporary pavement patch
  • Work is substantially complete

Winter Street Reconstruction

  • The City has contracted with Caracas Construction Corporation for the full depth reconstruction of Winter Street, including water & sewer mains and service connections and sidewalks
  • The project is substantially complete
  • Public Works and/or the Contractor will be on-site continuing post-construction inspections throughout the Fall

Projects to resume Spring 2024

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).


Facebook Twitter Email

Other News in Public Works

Annual Water Main Flushing

Posted on: March 30, 2026
City Seal Newsflash Image

Annual Water Quality Report

Posted on: March 11, 2026