[ARCHIVED] Construction for the Week of March 27th

Highway Division Updates

  • Last week, the Highway Division:
    • Repaired potholes on Acrebrook Drive, Arch Street, Elm Street, Linden Street, Reservoir Road, South Main Street & Winterberry Lane and at Jackson Street School, Northampton High School, RK Finn Ryan Road School & Smith Voc
    • Repaired, replaced or installed signs on Fairway Drive, Florence Road, Highland Avenue, Isabella Street, Lilly Street, Pleasant Street and Union Street
    • Graded Lawn Avenue and driveway & parking lot off Cooke Avenue (former Moose Lodge site)
    • Ordered salt and stockpiled salt deliveries
  • Annual ward street sweeping will resume in Spring 2023
  • To report a pothole, please submit a request via the Pothole Repair Form; the largest potholes are filled first to alleviate hazards to vehicles; as hazards arise and are identified, they will be addressed

Ongoing Projects


Dryads Green Extension

  • The City has contracted with Geeleher Enterprises, Inc. to perform emergency work to stabilize the slope southwest of Dryads Green Extension in order to protect a nearby sewer system
  • The Contractor has removed deadwood, installed crushed stone & riprap and made limited drain pipe repairs; the work area has been seeded & mulched and additional sediment controls have been installed
  • The path from Dryads Green Extension to the Mill River is closed until further notice
  • The DPW will periodically inspect this area throughout the winter to confirm site stability

I-91 Bridges over Route 5, the Railroad and Hockanum Road

  • MassDOT has contracted with J.F. White, Inc. to construct roadway improvements to I-91 and at Exit 23 (formerly Exit 18)
  • The project will replace the I-91 bridges over Route 5, the Railroad and Hockanum Road and construct safety and signal improvements at the exit interchange
  • The project is scheduled to be completed in phases by 2025
  • I-91 southbound, no traffic impacts are anticipated this week
  • I-91 northbound, right lane closure on Monday, Tuesday and Thursday, 9:00 a.m. to 2:00 p.m., this week
  • Route 5, lane shifts beneath the bridges for concrete deck placement are anticipated later in the week, weather permitting
  • Hockanum Road, no traffic impacts are anticipated this week
  • Questions about the project should be directed to MassDOT District 2, project #606552

Winter Street Reconstruction

  • The City has contracted with Caracas Construction Corporation for the full depth reconstruction of Winter Street, including water & sewer mains and service connections and sidewalks
  • The Contractor will be installing tree protection & environmental controls and will begin installing temporary water this week
  • Construction is scheduled to be complete by Fall 2023

Projects to Resume Spring 2023

Information & Notification

An overview of all current Public Works projects can be found by going to Current Projects.

Sign up for automatic notifications via the Notify Me system on the City's website. Please sign-in (at the top of the page) and then subscribe to the "Public Works" category under News Flash (at the bottom of the page).